On December 27, 2019, the National Research Institute of Mechanical Engineering (NARIME) together with the contractor consortium Lilama 10 Joint Stock Company (LILAMA 10) signed a contract with the Investor, the Power Project Management Board No. 3 – Branch of Vietnam Electricity Group, for package No. 19.2-CKTC: Fabrication, manufacturing and installation of equipment for the spillway structure cluster of the Bac Ai Pumped Storage Hydropower Project.
The contractor consortium Narime – Lilama 10 are reputable, capable and experienced contractors, trusted by the Investor to implement the package. The construction period of the package is 11 months.
The contractor consortium Narime – Lilama 10 commits to executing the package with quality, ensuring the set schedule, and meeting the requirements of the project investor.
Image from the contract signing ceremony